|
Oil & Gas Projects |
IPCO had extensive experience in the turnkey construction of onshore and offshore oil and gas facilities.
In Nigeria, IPCO has completed both Phase I and Phase II of the Calabar Oil Products Terminal and the Bonny Export Terminal. In Southern Thailand, IPCO through a joint venture installed a 210 km gas pipeline.
![]()
Bonny
Export Terminal
|
|
The Bonny
Export Terminal (US$251 m) in Port Harcourt of Nigeria. The project
involves the construction of an oil products export terminal, including
pipelines, sea island, tanks, pumping systems, and auxiliary facilities. |
IPCO arranged funding by means
of a revolving credit facility based on an oil product offtake agreement. The
credit facility was syndicated through major European banks.
This major project included detailed engineering,
purchasing of major components and on site construction and installation.
![]()
Oil Tanker Deballasting Facility
|
|
IPCO
was contracted to design and construct an onshore deballasting facility in
conjunction with a 50,000 DWT tanker product loading terminal on Pulau
Pesek, Singapore. The treatment facility receives tanker ballast water,
removes slop oil for processing and discharges a high grade of effluent,
meeting the stringent requirements set by the Ministry of Environment. |
![]()
Bontang Gas Pipeline
|
|
|
![]()
Melaka Lateral Gas Pipeline
|
|
IPCO
completed the contract to provide a 34 km gas pipeline system consisting of
20" dia and 12" dia pipeline, including two metering and
regulating sales stations for Petronas Gas Sdn Bhd, as part of Malaysia's
Peninsular Gas Utilisation Project. |
![]()
Mossel Bay Gas Platform
|
|
Following
competitive tender, IPCO was contracted to hook-up and commission an 8
leg, 16 well gas platform in the Indian Ocean. |
____________________________________________________________________________________
Champion Gas Slug Catcher (Lumut, Brunei)
|
|
Brunei Liquefied Natural Gas awarded IPCO a contract to construct a slug catcher and associated works. Paperwork, valves and fittings were installed on concrete sleepers and 4-pile reinforced concrete anchors. Access and supports and a test / production separator were also provided. A pipeline was laid to tie-in the offshore pipeline to the slug catcher. |
___________________________________________________________________________________
Onshore Gas Terminal Labuan Island, Malaysia
|
|
The Sabah Energy Corporation, created to provide facilities onshore and offshore to gather, process and transport gas for the Sabah Gas Utilisation project, contracted IPCO to construct the onshore Gas Terminal for the project.. Mechanical completion was achieved within the 20 month contract period. |
___________________________________________________________________________________
Crude Oil Loading Terminals, Iran
|
|
I PCO was contracted to a design and construct a US$160 million offshore crude oil loading terminal. The award, based on an IPCO alternative technical proposal, was the largest subsea pipeline installed by the bottom pull method.Despite difficult site conditions, the project was completed in 9 months, two months ahead of schedule. |
___________________________________________________________________________________
Gas Receiving And Distribution Terminal, Labuan Island Malaysia
|
|
I PCO was contracted to construct the gas receiving terminal and manifold center at the Ranca Ranca Industrial Estate on Labuan to receive and distribute gas from the offshore Samarang and Erb West Fields.The construction was completed, on schedule, in 3 months. |
___________________________________________________________________________________
Nosrat Platform, Nosrat Field, Persian Gulf
|
|
Ipco was contracted to design, fabricate and install a 4-pile wellhead platform, the centerpiece of the Nosrat Field Development. Work on this challenging project was completed within the tight contract period of 9 months. |
___________________________________________________________________________________
Offshore Facilities Hook-up, Norat Field, Persian Gulf
|
|
As part of the Nosrat Field Development, Ipco was contracted to hook-up a 12" submarine pipeline and 15 kV power cable to an existing production platform. Ipco was responsible for laying the pipeline and cable from the Nosrat Platform, which it also engineered and constructed. Switch gear was installed on the PP platform for the cable tie-in. Following hydrostatic and electrical testing, the hook-up was successfully completed, on schedule. |
___________________________________________________________________________________
Onshore Gas Pipeline, Labuan Island, Malaysia
|
|
As part of the massive Sabah Gas Utilization Project, Ipco was contracted to lay six kilometers of 18" gas transmission pipeline to connect the onshore gas receiving terminal, also constructed by Ipco, to the Ranca Ranca industrial estate on the other side of Labuan Island. The route for the buried pipeline passes through many types of terrain: hilly jungle, mangrove swamps and domestic and industrial developments. This presented a combination of installation problems that were successfully overcome. On completion, the pipeline was hydro-tested, flushed and then dried with methanol. |
___________________________________________________________________________________
Pipeline Shore Approach, Labuan Island, Malaysia
|
|
Brown & Root contracted Ipco to prepare the shore approach for two 14" submarine gas pipeline from the Samarang and Erb West fields, part of the massive Sabah Gas Utilization Project. The trench was then backfilled and the sheet piles removed. Final tie-in to the beach valves was carried out after hydro-testing of the submarine lines was completed. |
___________________________________________________________________________________
Submarine Gas Pipeline, Labuan Island, Malaysia
|
|
As part of the Sabah Energy Corporation’s massive Gas Utilization Project, Ipco was contracted to lay 11 kilometers of 18" gas transmission pipeline, four kilometers crossing a bay including tidal flats of sand, soft mud and extensive rock and coral outcrops. Due to poor ground conditions, engineered material was imported to backfill the trench, bringing the job to a successful close on schedule, 7 months after commencement. |
___________________________________________________________________________________
Talinpu Product Offloading Terminal, Taiwan
|
|
Ipco was awarded the contract for the design, supply and installation of a Single Mooring (SPM) Buoy and two 34" pipelines offshore Kaoshiung, Taiwan, for unloading diesel and naptha. Despite several occasions where the offshore work was halted due the typhoons, the project was successfully completed ahead of schedule. |
___________________________________________________________________________________